Saturday, April 25, 2009

Progress on the Walled Garden


Work on the arena within the walled garden has gone well during March and April because of the long dry spell. Russell has completed the corner of the wall where there is to be a door with steps on the outside which lead down to the stream. Russell is now working on the last corner on the inside of the wall. We can then start the ground work for the outdoor menage. Half of the drains have been laid so hopefully if we have any major downpours the inside of the walled should now no longer resemble a pond! There will not be enough stone from the demolition of the original wall to complete the ourside, but fortunately we have located a fallen down stone building at a local farm and the farmer has agreed to sell us some stone.