Thursday, January 17, 2008

The Barn goes up


PFG Fabrication have started putting up the barn despite the wet and windy weather. They had to pump out water from the holes that had been dug for the steel uprights before they could start. The roof is now complete and the guttering has been added. The sides which will be wooden boarding will take longer to put on and once that is completed a concrete floor will be laid.

All the tractors and other equipment are currently outside getting very wet and hopefully we will soon be able to get them all inside.

Friday, January 4, 2008

Another New Roof!

The new slate roof on the Animal Annex is now complete and because it looks so good we have decided to replace the roof on the Pigmy goat house and the future duck house.
Work has started on stripping off the old roof and replacing the timbers before we can re-slate.